FirstEnergy Completes Substation Project to Boost Service Reliability for Electric Customers in Lorain County
January 16, 2017
January 16, 2017
AKRON, Ohio, Jan. 16 -- FirstEnergy issued the following news release:
FirstEnergy (NYSE: FE) today announced that a $30 million transmission project has been energized in Elyria, Ohio, to meet rising demand for electricity driven by commercial and industrial load growth in the area.
The centerpiece of the project is a new 345/138-kilovolt (kV) substation that will increase the electric capacity available to serve Ohio Edison customers in Elyria, Lorain, Sheffield L . . .
FirstEnergy (NYSE: FE) today announced that a $30 million transmission project has been energized in Elyria, Ohio, to meet rising demand for electricity driven by commercial and industrial load growth in the area.
The centerpiece of the project is a new 345/138-kilovolt (kV) substation that will increase the electric capacity available to serve Ohio Edison customers in Elyria, Lorain, Sheffield L . . .