NRC Says Unplanned Shutdown at Perry Nuclear Plant Due to Coolant System Leakage
February 05, 2016
February 05, 2016
WASHINGTON, Feb. 5 -- The Nuclear Regulatory Commission issued the following preliminary notification report:
SUBJECT: UNPLANNED SHUTDOWN GREATER THAN 72 HOURS DUE TO REACTOR COOLANT SYSTEM LEAKAGE EXCEEDING TECHNICAL SPECIFICATION LIMITS AND SUBSEQUENT PLANT RESTART
On January 23, 2016, at 2100 EST, the Perry Nuclear Power Plant commenced a controlled plant shutdown due to an increasing trend in reactor coolant system leakage in the drywell. At 2122 EST, leakage ex . . .
SUBJECT: UNPLANNED SHUTDOWN GREATER THAN 72 HOURS DUE TO REACTOR COOLANT SYSTEM LEAKAGE EXCEEDING TECHNICAL SPECIFICATION LIMITS AND SUBSEQUENT PLANT RESTART
On January 23, 2016, at 2100 EST, the Perry Nuclear Power Plant commenced a controlled plant shutdown due to an increasing trend in reactor coolant system leakage in the drywell. At 2122 EST, leakage ex . . .